Stock Lists let you order equipment for your warehouse without creating a "stock" project. Build a list by hand, or let Jetbuilt fill one in from your Stock minimums, then create purchase orders right from the list.

Where to find it

Click Purchasing in the main menu, then click Stock Builder. The Purchasing menu also now holds:

  • PO Creator (formerly the global Purchasing tab), for ordering items across projects and stock lists by source.

  • Purchase Orders, the list of every PO in your account (moved from the Vendors area).

Setting your Stock List numbers

Stock Lists are numbered S-100, S-101 and so on by default. To change the prefix or the next number, go to Settings > Company > Numbering and edit the Stock List row.

Creating a Stock List

  1. In Stock Builder, click New Stock List.

  2. Enter a Name (for example, "Wire restock"). The Stock List ID fills in from your numbering settings, and you can change it.

  3. If you work in more than one office, choose the Office the list is for (likely your default/home office or HQ).

  4. Click OK.

Creating a restock list from your minimums

If you track minimum stock levels, Jetbuilt can build the list for you.

  1. In Stock Builder, click Create Restock List (when available).

  2. Enter a name, and choose an office if asked.

  3. Click OK.

Jetbuilt adds every item that has fallen below its Stock Min, with the quantity needed to get back to it: Order quantity = Stock Min − Available − On order

On order counts the item on purchase orders that haven't been received yet, so you don't reorder what's already on its way. Items without a Stock Min aren't added. To set minimums, see Minimum and Maximum Stock Inventory Levels.

Adding and editing items

  • Add items: click +Add Items, search for the item, enter the quantity and choose a source with Select Source.

  • Edit items: click Edit Items to change quantities and sources, and drag lines into a new order. Click Done when you're finished.

  • You can't lower a quantity below what's already been ordered. If you try, Jetbuilt tells you how many are already ordered.

Ordering items

  1. Open the stock list and check the items to order, or use the checkbox in the header to select them all. Lines that are fully ordered can't be checked.

  2. Click Order Items.

  3. The window lists each source and how many items will go on its PO. Jetbuilt creates one purchase order per source.

  4. Fill in the PO details, choose a PO template, and click Create.

If a line is partly ordered, only the remaining quantity is ordered. For example, if a line calls for 3 and 2 are already ordered, the new PO orders 1.

Ordering from PO Creator

You can also order stock list items in Purchasing > PO Creator, alongside project items from the same source. Choose a Source, then use the filter on the left to show All Stock Lists or a single list (for example, S-104). A PO can include both project items and stock list items.

Pull from Stock isn't available for stock list items, since they're being ordered for Stock.

Stock List statuses

Status

What it means

Not Ordered

Nothing on the list has been ordered yet.

Partially Ordered

Some items, or part of an item's quantity, have been ordered.

Closed

Everything on the list has been ordered. Closed lists move to ARCHIVE > Closed.

Use the OPEN filters in Stock Builder to show only the lists you still need to order from.

Renaming or deleting a Stock List

  • Rename: open the list, hover over its name, click the pencil, type the new name in Rename Stock List?, and click OK.

  • Delete: you can delete a list only while it has no items. Hover over the list's name, click the red trash icon, and click OK in Delete Stock List?. This can't be undone.

Finding stock purchase orders

All purchase orders, from projects and stock lists, are in Purchasing > Purchase Orders. The TYPE column shows what each PO holds, and you can filter by it:

Type

What's on the PO

Project

Items from one or more projects

Stock

Items from stock lists only

Mixed

Items from projects and stock lists

You can export or delete Stock and Mixed POs the same way as project POs. Deleting a PO marks its items as not ordered again.

Showing the project on your PO

In Designer, open your Purchase Order template, select the line item table, click Edit Options and check Project to add a PROJECT column. It's off by default. When a PO covers more than one project, the project field at the top of the PO shows Multiple – see line items.

Good to know

  • Office: a stock list's office does the job a project's office does. It sets the product database and prices you see when adding items, the list's currency, and the office address a stock-only PO ships to. The Office field shows only if you work in more than one office; otherwise your default office is used.

  • Receiving: receive stock list POs from Stock > Receive Items as usual. Because there's no project, received items go into Stock as available inventory instead of being allocated to a project.

  • Purchase Orders moved: the PO list used to live under Vendors > Purchase Orders. It's now under Purchasing for everyone.


If you have any questions, please reach out to us in chat support!